Peak Cluster has dropped its pipeline hub search area north of Gawsworth for a site north-east of Marton. A valve station is planned north-west of Bollington.

Peak Cluster no longer plans to put an above ground installation north of Gawsworth. The company behind the carbon dioxide pipeline has moved its main Cheshire junction south-west, to a site north-east of Marton.

Its new consultation documents, published on 12 November, also name the first local sites for smaller block valve stations. One is planned north-west of Bollington and another south of Disley. (Peak Cluster feedback booklet, section 3)

Overview

Peak Cluster’s November 2026 booklets for the Macclesfield area say the company has:

  • removed the search area for an above ground installation (AGI) north of Gawsworth and Moss Houses
  • moved that installation, the Central Feeder AGI, to north-east of Marton, about five miles south-west of Macclesfield
  • chosen a single route between Whaley Bridge and Marton, ending the alternative options south of Lyme Park, north of Bollington and west of Prestbury
  • picked preferred sites for block valve stations north-west of Bollington and south of Disley
  • moved the pipeline route near Gawsworth and Moss Houses, so that after passing North Rode it turns north-west, away from land allocated for future development

Comments close on Friday 18 December 2026. (Peak Cluster consultation hub)

The Gawsworth hub has moved

The Central Feeder AGI is where three branch pipelines would meet. They would come from Breedon’s Hope cement works, Tarmac’s Tunstead site and Holcim’s Cauldon site. (Peak Cluster feedback booklet, section 5)

Section 3 of the booklets says the company has “relocated the Central Feeder AGI south west”. It adds: “This means we have removed the AGI search area to the north of Gawsworth and Moss Houses.” (section 3)

Gawsworth Parish Council had listed a proposed above ground installation among its worries. Cheshire East councillors raised the same concern before the council objected to the scheme in October. At that point, the locations had not been published.

Peak Cluster says a typical AGI covers about 80m by 80m. It would hold pipework, valves, metering and control equipment and small kiosks. The company says the sites would not be permanently lit, and would make about as much noise as a small air conditioning unit. Each needs permanent road access for maintenance vehicles. (section 5)

A route is chosen north of Macclesfield

Earlier maps kept more than one possible line open north of the town. The section 3 booklet says Peak Cluster has now “selected our preferred route”. That has “removed route optionality south of Lyme Park, north of Bollington and west of Prestbury”.

The same section, from north-west of Whaley Bridge down to Marton, would carry two block valve stations:

  • one south of Disley, a village about eight miles north of Macclesfield
  • one north-west of Bollington, a town about three miles north of Macclesfield

The booklet does not name the fields. The exact sites are on the interactive map, along with the construction compounds and access roads.

A block valve station lets engineers shut off one stretch of pipe for maintenance or in an emergency. Peak Cluster says a typical one is about 25m by 25m, with low pipework, valves and a single-storey control kiosk. It also needs permanent road access. (section 3)

What else has changed

The booklets say the company received more than 5,500 responses to its first consultation earlier in 2026. Since then it has:

  • cut the corridor for permanent works from 300m to 100m in most areas
  • revised about 15% of the proposed route
  • confirmed the carbon dioxide would travel as a gas, at about 40 bar
  • removed a planned North Feeder AGI near Chapel-en-le-Frith

The pipe would be up to 36 inches across, buried with at least 1.2m of cover “wherever reasonably practicable”. Building it would need a working strip up to 40m wide. (section 3)

In section 4, which runs from Cauldon to Marton, the booklet says the route near Gawsworth and Moss Houses has moved. “After passing North Rode, the route now diverts northwest, avoiding land allocated for future development.” (section 4)

The council’s position

Cheshire East Council objected to the scheme in October. On 13 November it urged residents to respond to the consultation.

Council leader Councillor Nick Mannion said the objection “reflects councillors’ concerns about Peak Cluster’s current proposals and their potential implications for Cheshire East, including public safety and environmental impacts”. He asked residents “to read the proposals in detail, so all concerns can be presented back to them”.

The council is not the decision maker. Deputy leader Councillor Michael Gorman said it will send “a comprehensive response” after Full Council and Cabinet meetings “over the next two months”. He said formal plans are expected to be submitted towards the end of 2027. (Cheshire East Council)

Peak Cluster plans a second full consultation in summer 2027. It says that round will cover design, environmental assessments, construction, safety and land use.

What it means for you

If you live near Gawsworth, the hub that worried the parish has gone from the map. The pipeline route near the village has also been redrawn, so check the map for where it now runs.

If you live north-west of Bollington or south of Disley, a valve station site is now proposed near you. This is the first chance to comment on where it goes.

  • Check the interactive map, including its construction layer, for compounds and access roads.
  • Book the Gawsworth event on Friday 20 November at the Scout Hall, or the Cheshire webinar on Monday 30 November at 6.30pm.
  • Respond online or by post to Peak Cluster FREEPOST.
  • Comments close on Friday 18 December.